We have completed the conversion of a 11,000 m2 warehouse hall into production space. As part of the project, we carried out the following tasks:
- construction of a two-story office building inside the hall with an area of 600 m2,
- adaptation of the roof structure to the new ZL and PM fire zone divisions,
- construction of deep foundations and channels for production machines,
- installation of a pumping station with a cooling unit, heat exchanger, and tanks,
- installation of process water for production machines,
- installation of a compressed air system,
- enhancement of the ventilation and heating system's capacity,
- installation of ventilation exhausts from production lines,
- reconstruction of the sprinkler system,
- reconstruction of the smoke extraction system,
- adaptation to natural lighting requirements for production,
And so, in just 5 months from the start of work, the cable production hall was launched. This was a significant technical and scheduling challenge. We thank our team for their dedication and congratulate them on their effectiveness!